Building Remediation Cost Estimation
Expert Costing for Cladding Replacement, Fire Safety & Structural Repairs
From single-issue defects to comprehensive building upgrades.
Delivered in 3-8 days with ±5% accuracy.
Post-Grenfell Expertise - Cladding & fire safety compliance
Building Safety Act Knowledge - BSR/HRB requirements
Experience: Proven track record across UK, EU & Australia
Building Remediation: The Compliance Imperative
Industry Challenges
Building remediation projects face unique complexities and regulatory pressures:
Regulatory pressure - Building Safety Act, BSR compliance deadlines
Cost uncertainty - Hidden defects discovered during works
Occupied buildings - Works around residents, minimal disruption
Funding challenges - Grant applications, leaseholder charges
Complex interfaces - Multiple trades, phasing requirements
The Risk
“A 10% cost overrun on a £5M cladding remediation project represents £500,000 in unexpected costs. With BSR deadlines looming and complex funding arrangements, accurate cost estimation is critical for project viability and leaseholder consultation.”
Our Remediation Solution
Specialized 5D BIM for building remediation and compliance upgrades:
3-8 days for complete estimate (vs 6-8 weeks traditional)
Compliance expertise - Building Safety Act, BSR/HRB requirements
Phasing optimization - Minimize disruption, maintain occupancy
Contingency planning - Risk-based allowances for unknowns
Funding support - Documentation for grant applications
Proven Results
- Extensive remediation experience across UK, EU, and Australia
- Complex compliance projects delivered with precision
- Average 5 days from survey data to detailed estimate
- ±5% accuracy on 95% of projects
Remediation-Specific Services
Fast-Track Estimation
3-8 Day Turnaround
Perfect for: - Cladding remediation budgets - Fire safety upgrade costs - BSR compliance estimates - Grant funding applications
Compliance Costing
Building Safety Act
Expert knowledge of: - BSR/HRB requirements - Fire safety regulations - Structural assessment costs - External wall systems (EWS1)
Phasing & Logistics
Occupied Building Works
Critical for: - Resident decanting plans - Access strategies - Material delivery coordination - Minimize disruption periods
Multi-Scenario Analysis
Compare Remediation Options
Analyze impact of: - Different cladding systems - Phasing alternatives - Temporary works requirements - Value engineering options
Grant Application Support
Funding Documentation
Full service including: - Detailed cost breakdowns - Leaseholder consultation packs - BSF/ACM funding applications - Interim cost reports
Risk & Contingency
Unknown Defect Allowances
Expert assessment of: - Hidden defect probabilities - Contamination risks - Structural uncertainties - Interface complexities
Building Safety Regulator (BSR) Expertise
BSR Submission Cost Estimation
We provide detailed cost breakdowns for BSR-related activities:
Registration & Compliance (Typical Costs): - BSR registration application: £2,000-4,000 - Building Safety Case preparation: £15,000-35,000 - Resident engagement strategy: £5,000-12,000 - Mandatory occurrence reporting system: £3,000-8,000 - Annual compliance review: £8,000-15,000
Professional Team Requirements: - Principal Designer appointment - Principal Contractor obligations - Building Safety Manager (in occupation) - Accountable Person duties - Competence framework compliance - Change control management
Key BSR Cost Drivers We Quantify:
Enhanced documentation requirements
Digital information management (ISO 19650)
Competence verification systems
Gateway submission preparations
Golden thread information requirements
Resident engagement obligations
Remediation-Specific BSR Requirements
For existing HRBs requiring remediation, BSR compliance adds specific cost implications:
Enhanced Surveys & Assessments - Type 4 Fire Risk Assessment - Intrusive building investigations - Structural integrity reviews - External wall system (EWS1) assessments - Golden thread data creation
Compliance Documentation - Safety case updates during works - Change control procedures - Contractor competence verification - Mandatory occurrence reporting - Resident notification protocols
Post-Remediation Requirements - Updated building safety information - Revised safety case submission - As-built BIM models (ISO 19650) - Resident information updates - BSR notification of completion
Important BSR Deadline Context
All existing HRBs must be registered with BSR. Accountable Persons face significant penalties for non-compliance. Our cost estimates help building owners budget for mandatory compliance upgrades alongside remediation works.
Common Remediation Project Types
Understanding Remediation Complexity
Cladding Remediation
Building Height: Typically 18m+
Complexity: High
Timeline: 5-8 days
Typical Cost: £3,000-8,000 per unit
Scope Includes: - ACM/HPL cladding removal - Compliant system installation - Fire barriers & cavity barriers - External wall insulation (if required) - Balcony works & fire stopping - Scaffolding & protection - Building survey & testing
Fire Safety Upgrades
Building Type: Multi-occupancy
Complexity: Medium-High
Timeline: 4-6 days
Typical Cost: £1,500-4,000 per unit
Scope Includes: - Compartmentation upgrades - Fire door replacements - Smoke ventilation (AOV) - Fire alarm systems - Emergency lighting - Sprinkler systems (if required) - Wayfinding & signage
Structural Repairs
Building Age: Variable
Complexity: High
Timeline: 5-7 days
Typical Cost: £2,000-6,000 per unit
Scope Includes: - Concrete repairs (spalling) - Structural strengthening - Balcony reconstruction - Movement joint repairs - Waterproofing systems - Underpinning (if required) - Temporary propping
Key Cost Drivers in Remediation Projects
Typical Cladding Remediation Breakdown (per unit)
Cladding Works (40-45%)
- Strip existing cladding: £800-1,200/unit
- New compliant system: £1,500-2,800/unit
- Fire barriers & cavity barriers: £400-700/unit
- Insulation upgrades: £300-600/unit
- Subtotal: £3,000-5,300/unit
Access & Protection (20-25%)
- Scaffolding & edge protection: £800-1,400/unit
- Temporary weather protection: £300-600/unit
- Hoist/materials handling: £200-400/unit
- Site establishment: £200-350/unit
- Subtotal: £1,500-2,750/unit
Associated Works (15-20%)
- Window/door interface works: £400-700/unit
- Balcony remediation: £300-600/unit
- Roof interface works: £200-400/unit
- M&E modifications: £200-350/unit
- Subtotal: £1,100-2,050/unit
Project Costs (15-20%)
- Professional fees (12-15%): £700-1,200/unit
- Surveys & testing: £200-400/unit
- Resident liaison: £150-300/unit
- Contingency (10-15%): £500-900/unit
- Subtotal: £1,550-2,800/unit
Total Typical Range: £7,150-12,900 per unit
(For 50-100 unit buildings with ACM cladding)
NOTE: Actual costs vary significantly based on:
- Building height and façade area
- Extent of fire safety defects
- Access constraints and site conditions
- Occupied vs vacant possession
- Discovery of additional defects during works
Our Remediation Estimation Process
Initial Assessment & Data Review
Day 1 (4-6 hours)
What We Do: - Review building survey reports - Examine intrusive investigation data - Study fire risk assessments (FRA) - Review EWS1 forms & recommendations - Identify compliance requirements
Client Provides: - Building survey reports - Fire risk assessments - Structural reports (if available) - Existing drawings/as-builts - BSR/planning conditions
Output: Project scope confirmation
Scope Definition & Quantification
Days 1-3
What We Do: - Define remediation scope - Quantify cladding areas - Calculate fire barrier requirements - Assess structural repair extent - Identify interface works - Map resident impact zones
Technology: - BIM 5D extraction (if BIM available) - 2D takeoff from surveys - Building elevation analysis
Output: Complete quantity take-off (BOQ)
Cost Application & Risk Analysis
Days 3-5
What We Do: - Apply current remediation rates - Factor in access difficulties - Calculate phasing costs - Assess contamination risks - Include occupied building premiums - Apply risk-based contingencies (15-25%)
Database Sources: - BCIS remediation data - Live specialist quotes - Recent cladding projects
Output: Detailed cost estimate with risk register
Quality Review & Reporting
Days 5-7
What We Do: - Technical peer review - Check against benchmarks - Verify compliance scope - Prepare funding documentation - Create leaseholder summary - Schedule presentation
Deliverables: - Executive summary (2-3 pages) - Cost breakdown by work package - BOQ with quantities and rates - Funding application pack - Risk register & contingencies
Format: PDF + Excel workbooks
Presentation & Consultation Support
Day 7-8
What We Do: - Present findings to stakeholders - Explain cost drivers and risks - Review phasing options - Discuss resident communication - Support leaseholder consultation - Provide ongoing advice
Meeting Options: - In-person (UK only) - Video conference (all locations) - Leaseholder presentations
Support: 30 days post-delivery included
Typical Total Duration: 5-8 working days from survey data receipt to final report
Express Service: Available for urgent BSR deadlines (3-4 days) at 25% premium
Why Choose BIM Takeoff for Remediation?
Post-Grenfell Expertise
- Cladding remediation specialist knowledge
- Building Safety Act compliance
- BSR/HRB requirements understanding
- Fire safety system upgrades
Proven Speed
- 3-8 days typical turnaround
- Same-day updates for scope changes
- Express service for urgent deadlines
- 90% faster than traditional methods
Risk Management
- 15-25% contingencies for unknowns
- Risk register with probabilities
- Scenario planning for variations
- Hidden defect allowances
Funding Support
- Grant application documentation
- Leaseholder consultation packs
- BSF/ACM funding expertise
- Cost breakdown formats
Occupied Building Focus
- Phasing strategies developed
- Resident impact minimization
- Access planning optimization
- Decanting cost estimation
International Experience
- UK, EU, Australia markets
- Multiple building types handled
- Compliance standards knowledge
- Multi-currency reporting
Frequently Asked Questions
Q: Can you estimate remediation costs without intrusive surveys?
A: We can provide indicative budgets based on visual surveys and typical defect patterns, but we strongly recommend intrusive investigation before finalizing estimates. We typically include 20-25% contingency for non-intrusive estimates vs 10-15% for fully surveyed buildings.
Q: How do you handle unknown defects discovered during works?
A: Our estimates include risk-based contingencies (typically 15-25%) calculated from intrusive survey findings and industry benchmarks. We also provide a risk register identifying potential additional costs with probability assessments.
Q: Can you support Building Safety Fund (BSF) applications?
A: Yes, we regularly prepare cost documentation for BSF and other grant applications. We provide the detailed breakdown formats required by funding bodies and can support the technical review process.
Q: What about phasing to keep residents in occupation?
A: We specialize in occupied building remediation. Our estimates include phasing strategies, protection costs, temporary works, resident liaison, and the cost premium for working around occupants (typically 15-20% additional).
Q: How accurate are remediation estimates given the unknowns?
A: With proper intrusive surveys, we achieve ±5-8% accuracy on remediation projects (vs our standard ±5% for new build). The additional variance accounts for unexpected defects. We provide clear contingency breakdowns for transparency.
Q: Can you estimate alternative cladding systems for comparison?
A: Absolutely. We regularly compare different compliant cladding systems (brick slip, render, metal panels, terracotta) with full cost implications including performance characteristics, maintenance, and longevity considerations.
Q: What about asbestos or other hazardous materials?
A: We include allowances for asbestos surveys and removal when building age suggests likely presence. We work with specialist asbestos surveyors to refine removal costs and include proper disposal, air monitoring, and notification costs.
Q: What’s your fee structure for remediation projects?
A: Fees vary based on building size, defect complexity, and urgency. As a rough guide: - Small building (20-50 units): £3,500-6,000 - Medium building (50-100 units): £6,000-10,000 - Large building (100-200 units): £10,000-16,000 - Complex multi-block: £16,000-30,000
Express service (3-4 days) carries a 25% premium. Contact us for a specific quote.
Ready to Fast-Track Your Remediation Project?
Don’t Let BSR Deadlines Catch You Unprepared
Get accurate remediation costs for funding applications, leaseholder consultation, and project planning. Building Safety Act expertise you can trust.